Work In Progress: 29th March

Apr
02
2012

Almost summer like weather this week with hot and sunny conditions even in March! The railway opened for the 2012 season with steam locomotive SID operating with 3 carriages. A few visitors were about to keep Dave Tooke busy in the booking office/shop and Judy Williams with the tea rooms catering.

Posted By Nigel Thompson read more

Thames Valley Area Group Page Updated

Mar
31
2012
Thames Valley Area Group have been very busy of late with two recent presentations; March 19th Alcester Railway Circle where Chris Ward and Trevor Garnham explained the tremendous amount of work required just for the planning application.

Then on to Andover & District Model Engineering Society for a similar experience. Read more in their latest Newsletter HERE.
Posted By keith vingoe read more

Railway Children help rebuild L&B

Mar
29
2012
A few weeks ago, L&B Trustee, Secretary and Railway Company director Tony Nicholson received a donation towards the L&B (see letter below) all the way from Scotland.

Touched by the generosity of these two children - donating their week's pocket money - The team at Woody Bay wanted to express their thanks on behalf of all of us, so they posed for this photo:-
Posted By Martyn de Young read more

March Working Weekend Video and Photos

Mar
27
2012
This report and photos from Pete and Julia Snashall

Slightly later than intended, a few words about last weekend:

The March working party saw worked undertaken at 3 sites over the weekend in unseasonably fine weather - not the wind and rain that usually accompanies these weekends.

 
Posted By Martyn de Young read more

Volunteers Weekend and Locals Day

Mar
27
2012
This weekend was a very busy one indeed at Woody Bay Station - as well as elsewhere - as it was the weekend when we look to recruit new volunteers, have a working weekend for the regular volunteers and for the first time ran a Locals Day promotion.  

We  received several enquiries regarding volunteering on the railway and these are to be followed up. Meanwhile those that arrived for the volunteer working weekend spent Friday fettling trackwork at Woody Bay, Saturday clearing the old Blackmoor Hotel site and returned to Chelfham on Sunday.
Posted By keith vingoe read more

Work in Progress: 22nd March

Mar
22
2012

Last week, planning permission was granted for a "permanent" marquee to be erected for the whole of the season at Woody Bay. Martyn Budd and the team at Woody Bay prepared the groundworks and drainage using the excavator, with a hired-in dumper to move surplus earth across to the woodland. This week, a crushed limestone surface was laid, leveled and rolled smooth.

Posted By Martyn de Young read more

Work in Progress: 15th March

Mar
20
2012

 
Just a few views this week from during the misty conditions at Woody Bay as further work preparations for the coming operating season continued.
 
Posted By Martyn de Young read more

March working weekend: Friday 23rd - Sunday 25th

Mar
13
2012

This just in from Pete Snashall

March working weekend - Friday 23rd March - Sunday 25th March

Posted By keith vingoe read more

Coach 7 Underframe Completed!

Mar
12
2012
Coach 7 underframe completed at Boston Lodge 

The Underframe complete with bogies, brakes and coupling is now complete and will soon be dispatched to Great Yeldham.

Posted By keith vingoe read more

Work in Progress: 8th March

Mar
10
2012
With General Manager Martyn Budd away today on the IOW, Graham Varney and Nigel Thompson led the small group of volunteers tasked with some essential trackwork down the line in preparation for when passenger trains begin running again later this month.



1.HEDDON HALL with todays works train by the sleeper stacks near Bridge 67

Posted By Martyn de Young read more