Work in Progress - Thursday 30th April

In the morning a tele-handler fork lift was on site to move some stored rails from the overflow car park at Woody Bay onto the bogie flat wagon for eventual storage at Killington Lane. Then after relocating to Killington Lane the fork lift moved a large quantity of stored rail into stacks for easy access prior to their despatch by lorry for resale to another railway.
Back at Woody Bay staff and volunteers were involved in working on a variety of tasks around the railway today:

Photos: Nigel Thompson

1.  The digger loading coal into the works train from the car park.
     

2. Nigel cuts an old crooked rail in two in order to fit into the scrap metal skip.

3. Jim painting the inside of the doors in the new mess room

4. Martyn installing the steel plate floor in the replica Bogie Open wagon (L&BR No.12)

 

 


Corporate Supporters - Where to Stay