Work in Progress - Sunday 11th July

Woody Bay Transhipment siding (continued).

On the Saturday Martyn Budd with the digger regraded the formation to the exact lower uniform levels as surveyed by Alistair Hall using the high-tech laser sight system. So on Sunday the track gang were to relay the siding, connect at both ends and begin ballasting and levelling to the correct level.



1. Relaying the transhipment siding



2. Pausing whilst SID passes with the passenger train.



3. SID passes by again as work progresses.



4. Connecting a fiddly joint as the 50lb. weight rail meets the 40lb. weight rail



5. The surplus spoil from the regraded formation was landscaped into the bank.



6. The works train was brought alongside to begin dropping the recycled ballast back into the relaid siding.



7. Volunteers in shorts shovelling ballast.



8. Jacking and levelling to the correct height.



9. The gang pose on the siding after some slewing to create a smoother curve.



10. A track level view looking up the completed siding showing the new and improved alignment
.


No photo report for Thursday 15th as Nigel was enjoying his holiday visiting the Keighley & Worth Valley Railway.  However, Martyn Budd and Richard Willey, unaided, finished off the ballasting of the transhipment siding with some jacking and packing further up nearer the car park gate.  This project completed at virtually no cost will now enable heavier locomotives and rolling stock (such as LYD) to be safely transhipped at Woody Bay in order to operate at future Galas.

The siding is of course also regularly used during the shunt moves of various wagons required to continue to operate and maintain the railway.

Photos and Text Nigel Thompson