Over the past month, considerable work has been undertaken at the L&BR's second station at Chelfham. The small 'Friends of Chelfham Station' group has continued the early restoration work in and around the station building.
There was a major tidy-up of the stored equipment outside including a scrap-drive of a number of unneeded and irreparable items. A trailer-load of scrap metal, combined with a similar clear-out at Woody Bay yielded a considerable sum for the General Manager's Equipment fund for future signalling, engineering and heritage projects.
During December, volunteers at Chelfham have carried out signalling equipment restoration work within the sheds whilst others have focused on removing more of the plaster covering the original stonework from what was the front of the building, in preparation for the eventual removal of the 1960s extension over the platform.
After quite a busy November when many members were about for the half-term period and the forum weekends, unsurprisingly, fewer visitors have braved the cold and rain this month. However, please remember that Chelfham Station will be open every Sunday during the winter, when Trust members, friends and families are encouraged to visit and view the progress.
Words and pictures by Nigel Thompson